SR-874 Mainline Reconstruction… A year in progress

  • April 4, 2013

MDX 874 project is on track to finish before the end of 2013.  Most of the noise wall work on both sides of the expressway has been completed and we are shifting into MOT phase 2.  This second phase will move all traffic to the outside in order to finish the median construction.  In order to mitigate construction delays the Contractor is now providing interim MOT phases; shifting sections of the project from phase 1 into phase 2 in some areas of the project.

Miller bridge widening is almost complete and median widening in Sunset Dr is starting with foundation work. Galloway Bridge demolition is well underway and C-2 Canal widening is complete.  Roadway and drainage construction is completed on the outside widening ready to shift traffic.